CASE STUDY

Bridge Refurbishment

Client: Pannekoek GWW

Industry: Industrial

Scope: Bridge Refurbishment

Date: January 2018

Location: Netherlands

Products: RS 500P, RL 500PF & RA 500UW-LV

OVERVIEW

A New Build bridge required a protective coating system which could offer long-term corrosion protection.

CHALLENGE

A short time frame of 2 days was given for project completion.

Grit blasting was not permissible due to the damage it would cause to the surrounding environment. Full encapsulation would also incur a high cost and would significantly increase the project duration.

SOLUTION

Above the waterline. the substrate was high pressure water jetted (500bar). Two coats of wet & rust tolerant epoxy RL 500PF was then applied.

Below the waterline, the substrate was prepared using mechanical methods. This was followed by one primer coat of solvent-free, wet & rust tolerant epoxy RS 500P and one topcoat of Chemco’s specialised solvent-free underwater coating system RA 500UW-LV.

OUTCOME

The project was successfully completed to the great satisfaction of the client and within the strict 2 day time frame given for the project.

This project could only be completed within 2 days by using Chemco’s unique solution.

The same process will now be used for more bridges and other similar structures for this client.

BENEFITS

• Unique solution only offered by Chemco
• Excellent adhesion to sub-standard substrate conditions expected underwater
• No grit blasting required
• Significantly reduced contract duration
• Substantial time and cost savings

application water jetting rusted bridge beams

During Surface Preparation

application water jetting rusted bridge beams

During Surface Preparation

Contact Our Specialist Coating Advisors

Our coating specialists can suggest the right solution for your specific application.

Get more info on our
Products & Services…

Our coating specialists can suggest the right solution for your specific application.

Go to Top