CASE STUDY
Crude Oil Tank Refurbishment
Client: BP Dalmeny
Industry: Petrochemical
Scope: Crude Oil Tank Refurbishment
Date: June 2007
Location: UK
Products: RA 500M
OVERVIEW
Crude oil tank (75m diameter) internal lining required to be refurbished with a minimum 17 (12 + 5) years guarantee.
CHALLENGE
To carry out the work in as short as possible time scale. Reduce cost and duration, as any tank “out of service” costs a huge amount due to the size and volume of these tanks. The work should also be carried out in a safe manner in a working tank farm.
SOLUTION
Two coats of Epo-chem™ RA 564 solvent-free, wet tolerant glassflake epoxy @ 500µ per coat by airless spray with no requirement for ventilation or dehumidification.
OUTCOME
The technical benefits offered by this system ensured that the work was carried out on time, within budget and with no H&S issues.
BENEFITS
• No major delays
• Minimum 9 days reduction in contract duration
• Reduced H&S and Fire Precaution
• Reduced cost of equipment
• Chemco system will protect the steel substrate in excess of 17 years