CASE STUDY

Crude Oil Tank Refurbishment

Client: BP Dalmeny

Industry: Petrochemical

Scope: Crude Oil Tank Refurbishment

Date: June 2007

Location: UK

Products: RA 500M

OVERVIEW

Crude oil tank (75m diameter) internal lining required to be refurbished with a minimum 17 (12 + 5) years guarantee.

CHALLENGE

To carry out the work in as short as possible time scale. Reduce cost and duration, as any tank “out of service” costs a huge amount due to the size and volume of these tanks. The work should also be carried out in a safe manner in a working tank farm.

SOLUTION

Two coats of Epo-chem™ RA 564 solvent-free, wet tolerant glassflake epoxy @ 500µ per coat by airless spray with no requirement for ventilation or dehumidification.

OUTCOME

The technical benefits offered by this system ensured that the work was carried out on time, within budget and with no H&S issues.

BENEFITS

• No major delays
• Minimum 9 days reduction in contract duration
• Reduced H&S and Fire Precaution
• Reduced cost of equipment
• Chemco system will protect the steel substrate in excess of 17 years

dimly lit crude oil tank internals painted in white

Completed Application

dimly lit crude oil tank internals painted in white

Completed Application

Contact Our Specialist Coating Advisors

Our coating specialists can suggest the right solution for your specific application.

Get more info on our
Products & Services…

Our coating specialists can suggest the right solution for your specific application.

Go to Top